← Classes

Class 47: Limits on Damages I: Foreseeability + Mitigation

Remedies & Third Parties · Apr 12

By the end of class, you can

Today

Floor. ~40 min: R2d § 351 + Hadley. The doctrine the next class assumes you have covered.

Target. ~75 min: Floor + R2d § 352 + synthesis.

Foreseeability vs. mitigation: two filters, two moments

Every claimed loss runs a gauntlet of independent filters. Today isolates the first two:

The two are not the same fairness intuition wearing two hats. A loss can be foreseeable yet avoidable (cut at mitigation) or unforeseeable yet unavoidable (cut at foreseeability). Each filter operates on its own.

R2d § 351: Unforeseeability and Related Limitations on Damages

(1) Damages are not recoverable for loss that the party in breach did not have reason to foresee as a probable result of the breach when the contract was made.

(2) Loss may be foreseeable as a probable result of a breach because it follows from the breach

(a) in the ordinary course of events, or

(b) as a result of special circumstances, beyond the ordinary course of events, that the party in breach had reason to know.

(3) A court may limit damages for foreseeable loss by excluding recovery for loss of profits, by allowing recovery only for loss incurred in reliance, or otherwise if it concludes that in the circumstances justice so requires in order to avoid disproportionate compensation.

R2d § 352: Uncertainty as a Limitation on Damages

Damages are not recoverable for loss beyond an amount that the evidence permits to be established with reasonable certainty.

R2d § 350: Avoidability as a Limitation on Damages

Except as stated in subsection (2), damages are not recoverable for loss that the injured party could have avoided without undue risk, burden, or humiliation. The injured party is not precluded from recovery to the extent that he has made reasonable but unsuccessful efforts to avoid loss.

Damages limitations stack: filters 1 and 2

Four sequential filters applied to claimed damages: foreseeability (Hadley), certainty, avoidability/mitigation, and causation, each with an exit for excluded damages; surviving damages reach the bottom node as recoverable damages.
Today adds the mitigation filter below Hadley; foreseeability is ex ante, mitigation is ex post, and both operate independently on the same claimed loss.

The Hadley two-branch test

Two-branch Hadley foreseeability test: Branch 1, arises naturally from the breach (general damages, no notice required); Branch 2, in reasonable contemplation of both parties (special damages, notice required); losses outside both branches not recoverable.
Today's class uses this figure as a reference; the core work is the mitigation filter (R2d § 350), which operates independently after foreseeability.

Hadley v. Baxendale

9 Ex. 341, 156 Eng. Rep. 145 (1854)
Court of Exchequer

Rule. Damages for breach of contract are recoverable for losses (1) arising naturally, that is, according to the usual course of things, from the breach itself, or (2) such as may reasonably be supposed to have been in the contemplation of both parties at the time they made the contract as the probable result of its breach. Special damages not within either branch are not recoverable.

Worked example: Problem 26.1 — Freezer Failure

Facts. GeneCorp orders a $275,000 cryogenic freezer from Below Zero. GeneCorp gives performance specs but does not disclose that $25M in venture funding turns on demonstrating its concept to first customers. Below Zero delays installation two months. GeneCorp loses the financing.

Question. Can GeneCorp recover the $25M?

Analysis. R2d § 351 / Hadley branch 2: special damages recoverable only if reasonably contemplated. Specs alone are not notice of the financing risk. Below Zero is a refrigeration company, not a financial advisor; a two-month installation delay would not, in the ordinary course, signal $25M in lost funding. Loss exits at foreseeability.

Counter. A reasonable supplier of specialized equipment to a startup might foresee that delay risks investor confidence; $25M is not the ordinary measure of that risk.

Variation. GeneCorp tells Below Zero at contracting: "If you miss the install date, we lose VC funding contingent on a demo to investors." Now the loss enters branch 2, subject to certainty (was the funding really going to close?) and mitigation (could GeneCorp have rescheduled the demo?).

R2d § 350: Avoidability as a Limitation on Damages

Except as stated in subsection (2), damages are not recoverable for loss that the injured party could have avoided without undue risk, burden, or humiliation. The injured party is not precluded from recovery to the extent that he has made reasonable but unsuccessful efforts to avoid loss.

The mitigation principle: avoidable losses are not recoverable

R2d § 350: damages are not recoverable for loss that the injured party could have avoided without undue risk, burden, or humiliation. But the injured party is not barred from recovery to the extent he has made reasonable but unsuccessful efforts to avoid loss.

Two corollaries the rule does the work through:

Mitigation is not a punishment for the victim. It is an informational rule: it tells parties to plan for substitute performance the moment a breach is clear.

Rockingham County v. Luten Bridge Co.

35 F.2d 301 (4th Cir. 1929)
U.S. Court of Appeals for the Fourth Circuit

Rule. A party that receives notice of cancellation may not continue performance and thereby pile up damages. The non-breaching party's duty to mitigate begins on receipt of repudiation; expenses incurred after that point are not recoverable.

Worked example: Problem 26.3 — Shipping Servers

Facts. StreamTech contracts to sell $500,000 of servers to Alpha Streaming. Alpha repudiates two weeks before delivery, citing a market downturn. Despite the notice, StreamTech ships the servers anyway, incurring $15,000 in transportation costs. StreamTech finds no substitute buyer and sues for the full $500,000 plus the $15,000.

Question. Can StreamTech recover the $15,000 in shipping? What happens to the $500,000?

Analysis. The $15,000 is the Luten Bridge problem in UCC clothing. Alpha gave advance notice; under UCC § 2-704(2), a seller learning of repudiation before shipment must use reasonable commercial judgment to avoid unnecessary expense. The shipment was avoidable — the $15,000 is not recoverable (it would be recoverable as incidental damages under § 2-710 only if already shipped before notice).

The $500,000 turns on resale. Under UCC § 2-706, the seller must try to resell in good faith; recovery is then contract price minus resale price. If StreamTech resells for $400,000, Alpha owes $100,000. If StreamTech makes a genuine good-faith effort and the market truly will not absorb the goods, it may recover the full price under § 2-709(1)(b). Alpha's best argument throughout is failure to mitigate.

Stretch: mitigation as a planning tool

Variation on GeneCorp. Assume notice was given. Below Zero delays. GeneCorp learns of the delay the day it happens. GeneCorp could have rescheduled the investor demo at a cost of $40,000. It chose not to and lost the funding.

Under R2d § 350, the recoverable loss is the $40,000 reschedule cost, not the $25M financing loss. The injured party is expected to make reasonable efforts to reduce the loss; failure to do so does not bar recovery but limits damages to what could not have been avoided.

The mitigation duty is not punitive; it is informational. It tells parties to plan for substitute performance.

R2d § 355: Punitive Damages

Punitive damages are not recoverable for a breach of contract unless the conduct constituting the breach is also a tort for which punitive damages are recoverable.

What contract damages will NOT do: punitive and emotional-distress limits

Two categories of loss sit outside the ordinary expectation measure:

Both limits flow from the same premise as foreseeability and mitigation: damages track the reasonably expected economic value of the bargain, not the moral quality of the breach or the plaintiff's hurt feelings.

Stretch: Problem 26.2 — Jack's Furniture

Facts. Jack runs a small custom furniture business with inconsistent sales. He orders $25,000 of rare wood from Elite, telling Elite his client commission is "a big deal." Elite delivers defective material. Jack loses the commission. He claims $75,000 in lost profits, supported only by an unsigned email from the client and no prior earnings data.

Question. Recoverable?

Answer. Two filters fail. (1) R2d § 352 certainty: lost profits for a new or inconsistent business are speculative without historical or contractual baseline. (2) R2d § 351 foreseeability: "big deal" is not the kind of notice that puts Elite on the $75,000 risk.

What would change the result. Signed client contract + historical profit data + explicit notice to Elite of the magnitude. Then certainty and foreseeability both pass.

Class summary

Rules. R2d § 351 (foreseeability), § 350 (mitigation), § 352 (certainty), § 355 (no punitives).

Cases. Hadley v. Baxendale (foreseeability anchor) · Rockingham County v. Luten Bridge (mitigation: no piling up post-repudiation losses).

Punchline. Independent filters; a loss must pass all of them. Foreseeability is ex ante (breacher at contracting); mitigation is ex post (victim after breach); certainty runs throughout; and contract damages never punish.

Open question. What about the case where the parties have agreed in advance to a damages number? Next class: liquidated damages and Lake River. When does an agreed number bind, and when does the law strike it down?

Next time

Next class: Limits on Damages II: Certainty + Liquidated Damages

_Remedies & Third Parties_ · Apr 13

Read Lake River v. Carborundum. Posner refuses to enforce a liquidated-damages clause as a penalty, even between two sophisticated commercial parties. If both sides had lawyers and agreed on a number, why does the court second-guess them? Come ready to answer. You may be called.

1 / 21